Launder and single filtration chamber (filter box) heating system with the size of 17 inches
Task:
Warming-up of the filtration chamber and launder prior to casting and heating of melt during casting
Customer:
Krasnoyarsk Metallurgical Plant LLC, Krasnoyarsk, melting and casting unit No.1
Project year:
2016
Problems prior to implementation:
- Filtration chamber without cover and heating
- Launder without heating
- Big starting losses
Key Feauters:
- Power of the infrared heaters is 20 kW (900°С);
- Manual lifting drive
- Relay control circuit with SIEMENS and OWEN parts
Result:
Warming-up of the filtration chamber cartridge up to 600 °C
Reduction of starting losses
Possibility of heating during casting
Simple and convenient heating control