14.07.2018
Project for the bunker for Brochot ramming machine
10.07.2018

Development of project documentation for installation of a nonmagnetic plate of the electromagnetic stirrer

Task:

Upgrade of the existing Marconi 5 ton melting furnace in order to install an electromagnetic stirrer and produce AK12 alloys

Customer:

RIFAR CJSC, Gai

Project Year:

2018

Issues prior to implementation:

The furnace and foundations are not intended for the installation of an electromagnetic stirrer

The furnace for the alloys production was not used

Key Features:

  • Equipment layout drawings
  • Air duct system drawings
  • Metal structures revision drawings

Result:

The plate installation project was developed with retention of the initial stiffness of the hearth

The pit project of the pit was developed with retention of the foundation under the furnace supports

It is possible to install the LIM 500 inductor under the furnace