CASTING MACHINE OVERHAUL PROJECT
25.07.2018
Project for installation of nonmagnetic plate of the electromagnetic stirrer
13.07.2018

Development of project documentation for the lubrication heating machines of the casting units No. 4 and No.5 in the casthouse No.3

Task:

Upgrade of the system of lubrication feed to the molds of the casting machine in order to warp-up the oil tank and the pipe system in winter

Customer:

RUS-Engineering LLC for “RUSAL Krasnoyarsk” JSC, Casthouse No.3

Project Year:

2017

Issues prior to implementation:

  • Oil tank of small capacity without heating system
  • Heating of pipes only before the casting table
  • No oil level and temperature indication in the operator’s room

Key Features:

Metal structures, power equipment and automatic manufacturing process drawings

Result:

Capacity of the oil tank is increased up to 40 liters

Heating, temperature and oil level control system

Heating of pipes before molds with self-regulating heating cable

The control panel with indication of control parameters